Land Use Example
Alignment Alternatives
The general creek side determinations were chosen to minimize the number of tributary stream crossings. In the middle of reach E-B, four possible alternatives were considered due to the manhole depths necessary in Alternative One.
• Alternative One followed the typical project design along the west side. This alternative required extra depth manholes. (Manhole depths > 40’)
• Alternative Two followed the typical project design along the east side. However, this alternative encumbered the buildable portions of five lots.
• Alternative Two-A paralleled alternative two, but moved the alignment within 25’ of the bank. This alternative saved the buildable portion of the lots.
• Alternative Three moved the alignment significantly to the east, and is centered in an existing roadway. This alternative requires the reconstruction of the roadway and traffic detours due to the manhole depths. However this alternative eliminates the need for a future street main.
All alignment alternatives function from an engineering standpoint.

Work Item Unit Price   Alternate One  
      Qtys Total
Clearing $3,500 Ac 3.5 $12,250
12" DIP Sewer 6- 8 ft Deep $1 Lf    
12" DIP Sewer 8-10 ft Deep $1 Lf 14 $14
12" DIP Sewer 10-12 ft Deep $1 Lf 165 $165
12" DIP Sewer 12-14 ft Deep $1 Lf 48 $48
12" DIP Sewer 14-16 ft Deep $1 Lf 48 $48
12" DIP Sewer 16-18 ft Deep $1 Lf 48 $48
12" DIP Sewer 18-20 ft Deep $1 Lf 48 $48
12" DIP Sewer 20-22 ft Deep $1 Lf 48 $48
12" DIP Sewer 22-24 ft Deep $1 Lf 48 $48
12" DIP Sewer Over 24 ft Deep $1 Lf 918 $918
Sewer Manhole 0-6 Ft Deep $2,000 Ea 5 $10,000
Extra Depth Sewer Manhole $150 Lf 100 $15,000
15" Bore & Jack $1 Lf    
Pavement Repair $15 Sy    
Traffic Control        
Land Value        
         
Total       $38,635


Alternate Two   Alternate Two-A   Alternate Three  
Qtys Total Qtys Total Qtys Total
2 $7,000 2 $7,000 1 $3,500
776 $776 854 $854    
160 $160 124 $124 407 $407
210 $210 165 $165 90 $90
        98 $98
        98 $98
        101 $101
        103 $103
        103 $103
        103 $103
        252 $252
6 $12,000 6 $12,000 6 $12,000
15 $2,250 16 $2,400 51 $7,650
150 $150 150 $150 150 $150
        1600 $24,000
           
           
           
  $22,546   $22,693   $48,655

Based upon the cost estimates, Alternative Two-A is the recommended alternative for this reach. The entire recommended alignment affects approximately 30 parcels.

 
 