| Task Name |
Duration |
Start |
Finish |
| DEVELOP SCHEDULE |
1 day |
Mon 12/2/02 |
Mon 12/2/02 |
| DEVELOP WEB PAGE |
23 days |
Mon 12/30/02 |
Thu 1/30/03 |
| PRE-ALIGNMENT DETERMINATION |
5 days |
Mon 12/30/02 |
Mon 1/6/03 |
| POST-PRELIMINARY ALIGNMENT DETERMINATION |
5 days |
Fri 1/24/03 |
Thu 1/30/03 |
| PROJECT STUDY PHASE |
27 days |
Mon 12/16/02 |
Thu 1/23/03 |
| SURVEYING |
13.38 days |
Mon 12/16/02 |
Tue 1/7/03 |
| DEED RESEARCH |
5.13 days |
Mon 12/16/02 |
Mon 12/23/02 |
| CONTACT PROPERTY OWNERS |
3.5 days |
Mon 12/23/02 |
Mon 12/30/02 |
| ESTABLISH CONTROL MONUMENTS |
6.38 days |
Fri 12/27/02 |
Tue 1/7/03 |
| COMPILE STRIP MAP |
6 days |
Wed 12/18/02 |
Fri 12/27/02 |
| ROUTE ALIGNMENT EVALUATIONS |
13 days |
Mon 12/30/02 |
Thu 1/16/03 |
| FIELD RECON |
3 days |
Mon 12/30/02 |
Thu 1/2/03 |
| FIELD RECON TECH MEMORANDA |
3 days |
Fri 1/3/03 |
Tue 1/7/03 |
| ANAYLIS OF ALTERNATIVES |
5 days |
Wed 1/8/03 |
Tue 1/14/03 |
| CMU REVIEW AND APPROVAL |
2 days |
Wed 1/15/03 |
Thu 1/16/03 |
| STUDY PHASE REPORT |
5 days |
Fri 1/17/03 |
Thu 1/23/03 |
| PRELIMINARY DESIGN |
103 days |
Fri 1/17/03 |
Tue 6/10/03 |
| DESIGN SURVEYS |
24 days |
Fri 1/17/03 |
Wed 2/19/03 |
| FIELD RECON TO ESTABLISH MH'S |
3 days |
Fri 1/17/03 |
Tue 1/21/03 |
| PERFORM SURVEYS |
21 days |
Wed 1/22/03 |
Wed 2/19/03 |
| ENVIRONMENTAL ASSESSMENT / PERMITTING |
20 days |
Fri 1/24/03 |
Thu 2/20/03 |
| PIPE HYDRAULIC DESIGN |
39 days |
Fri 1/24/03 |
Wed 3/19/03 |
| SYSTEM MODEL |
5 days |
Fri 1/24/03 |
Thu 1/30/03 |
| EVALUATE SIZE OPTIONS |
4 days |
Fri 1/31/03 |
Wed 2/5/03 |
| PREPARE PLAN/PROFILE STRIP MAP |
20 days |
Thu 2/6/03 |
Wed 3/5/03 |
| PREPARE COST ESTIMATE |
5 days |
Thu 3/6/03 |
Wed 3/12/03 |
| DEFINE R/W AND EASEMENTS |
5 days |
Thu 3/6/03 |
Wed 3/12/03 |
| REVIEW CMU STANDARDS |
3 days |
Thu 3/6/03 |
Mon 3/10/03 |
| TECHNICAL DESIGN MEMORANDA |
5 days |
Thu 3/13/03 |
Wed 3/19/03 |
| PROJECT REVIEWS |
5 days |
Thu 3/20/03 |
Wed 3/26/03 |
| CONSTRUCTABILITY |
5 days |
Thu 3/20/03 |
Wed 3/26/03 |
| EA ISSUES |
5 days |
Thu 3/20/03 |
Wed 3/26/03 |
| PRESENTATION TO PROJECT TEAM |
0 days |
Wed 3/26/03 |
Wed 3/26/03 |
| PRELIM DESIGN SUBMITTAL |
54 days |
Thu 3/27/03 |
Tue 6/10/03 |
| PRELIMINARY PLANS |
40 days |
Thu 3/27/03 |
Wed 5/21/03 |
| OUTLINE OF SPECIFICATIONS |
2 days |
Thu 5/22/03 |
Fri 5/23/03 |
| PRELIMINARY EA |
20 days |
Thu 3/27/03 |
Wed 4/23/03 |
| RIGHT OF WAY RECOMMENDATIONS |
5 days |
Mon 5/26/03 |
Fri 5/30/03 |
| LISTING OF EASEMENTS |
2 days |
Mon 6/2/03 |
Tue 6/3/03 |
| LISTING OF REQUIRED PERMITS |
1 day |
Thu 4/24/03 |
Thu 4/24/03 |
| UPDATE COST ESTIMATE |
5 days |
Wed 6/4/03 |
Tue 6/10/03 |
| CONSTRUCTION DOCUMENTS |
178 days |
Thu 4/24/03 |
Mon 12/29/03 |
| SEWER CONSTRUCTION DOCUMENTS |
45 days |
Thu 4/24/03 |
Wed 6/25/03 |
| INCORPORATE EA COMMENTS |
3 days |
Thu 4/24/03 |
Mon 4/28/03 |
| PREPARE DETAILED HORIZONTAL AND VERTICAL |
10 days |
Mon 6/2/03 |
Fri 6/13/03 |
| EROSION CONTROL PLANS |
3 days |
Mon 6/16/03 |
Wed 6/18/03 |
| GENERAL CONSTRUCTION NOTES |
2 days |
Mon 6/16/03 |
Tue 6/17/03 |
| GENERAL CONSTRUCTION DETAILS |
5 days |
Mon 6/16/03 |
Fri 6/20/03 |
| PREPARE BID DOCUMENTS |
3 days |
Mon 6/23/03 |
Wed 6/25/03 |
| ENVIRONMENTAL ASSESSMENT / PERMITTING |
20 days |
Thu 5/22/03 |
Wed 6/18/03 |
| GEOTECHNICAL INVESTIGATIONS |
10 days |
Thu 5/22/03 |
Wed 6/4/03 |
| CONSTRUCTABILTIY REVIEW |
3 days |
Mon 6/23/03 |
Wed 6/25/03 |
| FINAL DESIGN SUBMITTAL / REVIEW |
14 days |
Wed 12/10/03 |
Mon 12/29/03 |
| INCORPORATE SPECIAL R/W ISSUES |
5 days |
Wed 12/10/03 |
Tue 12/16/03 |
| SUBMIT CONSTRUCTION PACKAGE TO CMU |
0 days |
Tue 12/16/03 |
Tue 12/16/03 |
| MEETING WITH CMU ADMINISTRATION |
1 day |
Wed 12/17/03 |
Wed 12/17/03 |
| REVISIONS PER CMU |
5 days |
Thu 12/18/03 |
Wed 12/24/03 |
| FINAL CONSTRUCTION ESTIMATE |
2 days |
Thu 12/25/03 |
Fri 12/26/03 |
| PREPARE BID AND CONSTRUCTION SCHEDULE |
3 days |
Thu 12/25/03 |
Mon 12/29/03 |
| REGULATORY AGENCY REVIEW |
92 days |
Thu 6/19/03 |
Fri 10/24/03 |
| NCDWQ |
90 days |
Mon 6/23/03 |
Fri 10/24/03 |
| EROSION CONTROL |
45 days |
Thu 6/19/03 |
Wed 8/20/03 |
| EASEMENT EXHIBIT SURVEYS |
136 days |
Wed 6/4/03 |
Wed 12/10/03 |
| MAPPING TO DESCRIBE EACH PARCEL AND EASEM |
10 days |
Wed 6/4/03 |
Tue 6/17/03 |
| EASEMENT EXHIBITS FOR ACQUISITION |
10 days |
Wed 6/11/03 |
Tue 6/24/03 |
| REVISE EXHIBITS |
1 day |
Wed 12/10/03 |
Wed 12/10/03 |
| RIGHT OF WAY ACQUISITION |
210 days |
1/1/2004 |
7/30/2004 |
| COMPLETE PLANS |
0 days |
Apr-04 |
Apr-04 |
| BIDDING AND AWARD |
30 days |
Tue 12/30/03 |
Mon 2/9/04 |
| ADVERTISE |
15 days |
Tue 12/30/03 |
Mon 1/19/04 |
| ORIGINAL BID OPENING |
0 days |
7/13/2004 |
7/13/2004 |
| SECOND BID OPENING |
0 days |
7/29/2004 |
7/29/2004 |
| AWARD |
0 days |
Aug-04 |
Aug-04 |
| BEGIN CONSTRUCTION OF 21" SECTION |
90 days |
Oct-04 |
Feb-05 |
| BEGIN CONSTRUCTION OF 18' SECTION |
120 days |
Feb-05 |
Jun-05 |
| BEGIN CONSTRUCTION OF 15' SECTION |
35 days |
Jun-05 |
July-05 |
| COMPLETION OF LINE "A" EXCEPT TUNNEL BLAIR RD. |
180 days |
Oct-04 |
Jul-05 |
| BEGIN CONSTRUCTION LINE B 12' PIPE |
60 days |
May-05 |
Jul-05 |
| COMPLETION LINE "B" EXCEPT BORE HWY 24/27 |
120 days |
May-05 |
Sep-05 |
| COMPLETED WALLS WITH CMUD, BUCKEYE, CESI |
|
|
Oct-05 |
| BLAIR RD. TUNNEL EXCAVATION BEGINS |
120 days |
Jan-06 |
May-06 |