Task Name Duration Start Finish
DEVELOP SCHEDULE 1 day Mon 12/2/02 Mon 12/2/02
DEVELOP WEB PAGE 23 days Mon 12/30/02 Thu 1/30/03
PRE-ALIGNMENT DETERMINATION 5 days Mon 12/30/02 Mon 1/6/03
POST-PRELIMINARY ALIGNMENT DETERMINATION 5 days Fri 1/24/03 Thu 1/30/03
PROJECT STUDY PHASE 27 days Mon 12/16/02 Thu 1/23/03
SURVEYING 13.38 days Mon 12/16/02 Tue 1/7/03
DEED RESEARCH 5.13 days Mon 12/16/02 Mon 12/23/02
CONTACT PROPERTY OWNERS 3.5 days Mon 12/23/02 Mon 12/30/02
ESTABLISH CONTROL MONUMENTS 6.38 days Fri 12/27/02 Tue 1/7/03
COMPILE STRIP MAP 6 days Wed 12/18/02 Fri 12/27/02
ROUTE ALIGNMENT EVALUATIONS 13 days Mon 12/30/02 Thu 1/16/03
FIELD RECON 3 days Mon 12/30/02 Thu 1/2/03
FIELD RECON TECH MEMORANDA 3 days Fri 1/3/03 Tue 1/7/03
ANAYLIS OF ALTERNATIVES 5 days Wed 1/8/03 Tue 1/14/03
CMU REVIEW AND APPROVAL 2 days Wed 1/15/03 Thu 1/16/03
STUDY PHASE REPORT 5 days Fri 1/17/03 Thu 1/23/03
PRELIMINARY DESIGN 103 days Fri 1/17/03 Tue 6/10/03
DESIGN SURVEYS 24 days Fri 1/17/03 Wed 2/19/03
FIELD RECON TO ESTABLISH MH'S 3 days Fri 1/17/03 Tue 1/21/03
PERFORM SURVEYS 21 days Wed 1/22/03 Wed 2/19/03
ENVIRONMENTAL ASSESSMENT / PERMITTING 20 days Fri 1/24/03 Thu 2/20/03
PIPE HYDRAULIC DESIGN 39 days Fri 1/24/03 Wed 3/19/03
SYSTEM MODEL 5 days Fri 1/24/03 Thu 1/30/03
EVALUATE SIZE OPTIONS 4 days Fri 1/31/03 Wed 2/5/03
PREPARE PLAN/PROFILE STRIP MAP 20 days Thu 2/6/03 Wed 3/5/03
PREPARE COST ESTIMATE 5 days Thu 3/6/03 Wed 3/12/03
DEFINE R/W AND EASEMENTS 5 days Thu 3/6/03 Wed 3/12/03
REVIEW CMU STANDARDS 3 days Thu 3/6/03 Mon 3/10/03
TECHNICAL DESIGN MEMORANDA 5 days Thu 3/13/03 Wed 3/19/03
PROJECT REVIEWS 5 days Thu 3/20/03 Wed 3/26/03
CONSTRUCTABILITY 5 days Thu 3/20/03 Wed 3/26/03
EA ISSUES 5 days Thu 3/20/03 Wed 3/26/03
PRESENTATION TO PROJECT TEAM 0 days Wed 3/26/03 Wed 3/26/03
PRELIM DESIGN SUBMITTAL 54 days Thu 3/27/03 Tue 6/10/03
PRELIMINARY PLANS 40 days Thu 3/27/03 Wed 5/21/03
OUTLINE OF SPECIFICATIONS 2 days Thu 5/22/03 Fri 5/23/03
PRELIMINARY EA 20 days Thu 3/27/03 Wed 4/23/03
RIGHT OF WAY RECOMMENDATIONS 5 days Mon 5/26/03 Fri 5/30/03
LISTING OF EASEMENTS 2 days Mon 6/2/03 Tue 6/3/03
LISTING OF REQUIRED PERMITS 1 day Thu 4/24/03 Thu 4/24/03
UPDATE COST ESTIMATE 5 days Wed 6/4/03 Tue 6/10/03
CONSTRUCTION DOCUMENTS 178 days Thu 4/24/03 Mon 12/29/03
SEWER CONSTRUCTION DOCUMENTS 45 days Thu 4/24/03 Wed 6/25/03
INCORPORATE EA COMMENTS 3 days Thu 4/24/03 Mon 4/28/03
PREPARE DETAILED HORIZONTAL AND VERTICAL 10 days Mon 6/2/03 Fri 6/13/03
EROSION CONTROL PLANS 3 days Mon 6/16/03 Wed 6/18/03
GENERAL CONSTRUCTION NOTES 2 days Mon 6/16/03 Tue 6/17/03
GENERAL CONSTRUCTION DETAILS 5 days Mon 6/16/03 Fri 6/20/03
PREPARE BID DOCUMENTS 3 days Mon 6/23/03 Wed 6/25/03
ENVIRONMENTAL ASSESSMENT / PERMITTING 20 days Thu 5/22/03 Wed 6/18/03
GEOTECHNICAL INVESTIGATIONS 10 days Thu 5/22/03 Wed 6/4/03
CONSTRUCTABILTIY REVIEW 3 days Mon 6/23/03 Wed 6/25/03
FINAL DESIGN SUBMITTAL / REVIEW 14 days Wed 12/10/03 Mon 12/29/03
INCORPORATE SPECIAL R/W ISSUES 5 days Wed 12/10/03 Tue 12/16/03
SUBMIT CONSTRUCTION PACKAGE TO CMU 0 days Tue 12/16/03 Tue 12/16/03
MEETING WITH CMU ADMINISTRATION 1 day Wed 12/17/03 Wed 12/17/03
REVISIONS PER CMU 5 days Thu 12/18/03 Wed 12/24/03
FINAL CONSTRUCTION ESTIMATE 2 days Thu 12/25/03 Fri 12/26/03
PREPARE BID AND CONSTRUCTION SCHEDULE 3 days Thu 12/25/03 Mon 12/29/03
REGULATORY AGENCY REVIEW 92 days Thu 6/19/03 Fri 10/24/03
NCDWQ 90 days Mon 6/23/03 Fri 10/24/03
EROSION CONTROL 45 days Thu 6/19/03 Wed 8/20/03
EASEMENT EXHIBIT SURVEYS 136 days Wed 6/4/03 Wed 12/10/03
MAPPING TO DESCRIBE EACH PARCEL AND EASEM 10 days Wed 6/4/03 Tue 6/17/03
EASEMENT EXHIBITS FOR ACQUISITION 10 days Wed 6/11/03 Tue 6/24/03
REVISE EXHIBITS 1 day Wed 12/10/03 Wed 12/10/03
RIGHT OF WAY ACQUISITION 210 days 1/1/2004 7/30/2004
 COMPLETE PLANS 0 days Apr-04 Apr-04
BIDDING AND AWARD 30 days Tue 12/30/03 Mon 2/9/04
ADVERTISE 15 days Tue 12/30/03 Mon 1/19/04
ORIGINAL BID OPENING 0 days 7/13/2004 7/13/2004
SECOND BID OPENING 0 days 7/29/2004 7/29/2004
AWARD 0 days Aug-04 Aug-04
BEGIN CONSTRUCTION OF 21" SECTION 90 days Oct-04 Feb-05
BEGIN CONSTRUCTION OF 18' SECTION 120 days Feb-05 Jun-05
BEGIN CONSTRUCTION OF 15' SECTION 35 days Jun-05 July-05
COMPLETION OF LINE "A" EXCEPT TUNNEL BLAIR RD. 180 days Oct-04 Jul-05
BEGIN CONSTRUCTION LINE B 12' PIPE 60 days May-05 Jul-05
COMPLETION LINE "B" EXCEPT BORE HWY 24/27 120 days May-05 Sep-05
COMPLETED WALLS WITH CMUD, BUCKEYE, CESI     Oct-05
BLAIR RD. TUNNEL EXCAVATION BEGINS 120 days Jan-06 May-06
 
 