for a printable version click here

ITEM
DESCRIPTION
Quantity
Unit Price
Total
  CLEAR CREEK BASIN SANITARY SEWER FORCE MAIN & FUTURE GRAVITY SEWER– PROJECT # 292-02-672: FORCE MAIN      
1 For Furnishing and Installing Force Main Pipe, with Grooved End Restrained Joints, as specified, complete in place – 12-Inch PVC Force Main Pipe (Pressure Class-200)      
A. 12-inch PVC Force Main Pipe      
1 0’ to 6’ Depth 63 $54.90 $3,458.70
2 6’ to 8’ Depth 239 $56.90 $13,599.10
3 8’ to 10’ Depth 1,721 $59.50 $102,399.50
4 10’ to 12” Depth 1,232 $62.85 $77,431.20
5 12’ to 14’ Depth 2,822 $67.25 $189,779.50
6 14’ to 16’ Depth 2,638 $73.25 $193,233.50
7 16’ to 18’ Depth 1,301 $82.10 $106,812.10
8 Over 18’ Depth 690 $90.65 $62,548.50
2 For Substituting Restrained Joint Ductile Iron Pipe, as specified, complete in place. (Add on to Item 1) – 12-Inch Ductile Iron Pipe (Pressure Class-350) 100 $22.35 $2,235.00
3 Not Used      
4 For Furnishing and Installing Anti-Seep Collars, as specified, complete in place. 8 $435.00 $3,480.00
5 For Connection to Sanitary Sewer MH at Blair Road (NC-51), as specified, complete in place. 1 $2,375.00 $2,375.00
6 For Furnishing and Installing Stone Bedding and Stabilization, as specified, complete in place. (For Undercut Excavation as directed by the Engineer) 1,000 $24.00 $24,000.00
7 For Furnishing and Installing Additional Fittings not indicated on the Plans, as specified, complete in place. 200 $4.50 $900.00
8 For Removal and Disposal of Existing Manholes as shown on the Plans, as specified, and as directed by the Engineer. 2 $575.00 $1,150.00
9 For Jacking 12” PVC Force Main Carrier Pipe into existing 18” DIP Casing Pipe under I-485, as shown on the Plans, as specified, and as directed by the Engineer. 414 $73.30 $30,346.20
10 For Cutting (Sawing) and Replacing All Asphaltic Pavement as specified, complete in place. (Also including any concrete encountered under as asphaltic surface treatment) – H-Binder & I-1 or I-2 273 $35.50 $9,705.15
11 For Cutting and Replacing Concrete Driveways and Walkways, as specified, complete in place – Concrete Driveways (minimum 6" deep with wire reinforcing) 39 $47.85 $1,866.15
12 For Furnishing and Installing Soft Shoulder Signs as specified, complete in place. 2 $143.00 $286.00
13 For Constructing and Maintaining Various Erosion Control Devices, as specified.      
A Silt Fence 14,600 $2.10 $30,660.00
B Temporary Stream Crossings/Stream Bank Restoration 12 $5,390.00 $64,680.00
C Temporary Construction Entrance 2 $1,080.00 $2,160.00
D Rock Check Dams 10 $75.00 $750.00
14 For Furnishing and Installing Stone Rip-Rap, as specified, complete in place. 50 $30.00 $1,500.00
15 For Furnishing and Installing Brass Disk Marker, as specified, complete in place. 2 $160.00 $320.00
16 For Furnishing and Installing Force Main Marker Posts, as specified, complete in place. 40 $100.00 $4,000.00
17 For Solid Rock Excavation, as specified, complete in place ($40/CY minimum). 7,000 $40.00 $280,000.00
18 For Fertilizer, Seed, and Mulching, as specified, complete in place 53,995 $0.55 $29,697.25
19 For Clearing, Grubbing & Disposal of Debris, as specified, complete in place 10,706 $4.20 $44,965.20
20 For Hydrostatic and Leakage Tests, as specified, complete in place. 11,120 $0.70 $7,784.00
21 Not Used      
  Sum for project 292-02-672, Force Main     $1,292,122.05
  CLEAR CREEK BASIN SANITARY SEWER FORCE MAIN & FUTURE GRAVITY SEWER– PROJECT # 292-02-672: GRAVITY SEWER      
22 For Furnishing and Installing Stone Bedding and stabilization, as specified, complete in place. 20 $24.00 $480.00
23 For Furnishing and Installing (Dry-Bore) with Steel Encasement, as specified, complete in place.      
A 24-inch Diameter Casing (0.250”) 57 $333.00 $18,981.00
B Concrete Barriers (Bore Pits) 50 $3.60 $180.00
24 For Mobilization, Excavation and Backfill for Bore Installation, as specified, complete in place. 1 $4,185.00 $4,185.00
25 For Grouting Incomplete Encasing Pipe, as specified, complete in place – 24-inch Encasing Pipe 14 $265.00 $3,710.00
26 For Installing 48-inch Tunnel (12 Gauge), Anchoring the Carrier Pipe, and necessary mortar end sealing, as specified, complete in place. The unit price will not be less than the unit bid price for boring. 14 $1,815.00 $25,410.00
27 For Furnishing and Installing Soft Shoulder Signs as specified, complete in place. 4 $143.00 $572.00
28 For Constructing and Maintaining Various Erosion Control Devices, as specified.      
A Silt Fence 540 $2.10 $1,134.00
29 For Furnishing and Installing Gravity Sanitary Sewer Pipe, as specified, complete in place.      
A 12-inch Sanitary Sewer Pipe      
1 0’ to 6’ Depth 56 $46.75 $2,618.00
2 6’ to 8’ Depth 50 $49.10 $2,455.00
3 8’ to 10’ Depth 25 $59.15 $1,478.75
4 10’ to 12’ Depth 222 $66.25 $14,707.50
5 12’ to 14’ Depth 59 $76.60 $4,519.40
30 For Removing Existing 8” Sanitary Sewer Pipe, as specified, complete in place. (Add onto Item 29) 236 $10.20 $2,407.20
31 For Removing Existing 8” Sanitary Sewer Pipe in 18” Steel Casing and Replacing with 12”, as specified, complete in place. 110 $64.00 $7,040.00
32 For Pipe Bursting Existing 8” Sanitary Sewer Pipe and Increasing Size to 12”, as specified, complete in place. 423 $221.00 $93,483.00
33 For Connection to Existing Sanitary Sewer MH at Sta. 116 + 45.56, as specified, complete in place. 1 $2,316.00 $2,316.00
34 For Substituting Ductile Iron Pipe, as specified, complete in place.      
A 12” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 29) 50 $13.85 $692.50
35 For Basic 0’ to 6’ Depth, Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes      
1 Bolted Down Frame and Cover 3 $1,271.00 $3,813.00
36 For Extra Depth, All Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes 11 $113.00 $1,243.00
37 For adding a PVC Liner in the Manholes, as specified, complete in place.      
A For Basic 0’ to 6’ Depth Manholes 3 $916.00 $2,748.00
B For Extra Depth, all Manholes 11 $153.00 $1,683.00
38 For Furnishing and Installing Odor Control MH, as specified, complete in place. 1 $25,290.00 $25,290.00
39 Not Used      
40 For Fertilizer, Seed, and Mulching, as specified complete in place. 1,160 $0.55 $638.00
41 For Testing for Exfiltration, as specified complete.      
A Sanitary Sewer Pipe      
1 12-inch Pipe 945 $0.60 $567.00
B Manholes      
1 4-foot Diameter Manholes 3 $80.00 $240.00
42 For Removal and Disposal of Existing Above Ground Storage Tank at STA. 114+50, as specified. 1 $1,890.00 $1,890.00
43 For Abandonment of Existing Well at STA. 114+63 in accordance with NCDENR Rules, Regulations, and Specifications. 1 $600.00 $600.00
44 For Reconstructing Service Lateral Connections, as specified, complete in place. 5 $895.00 $4,475.00
45 For Removal and Replacement of Landscape Items, as specified, as directed by the Engineer, complete in place. 1 $7,325.00 $7,325.00
  Sum for project 292-02-672, Gravity sewer     $236,881.35
  CLEAR CREEK GRAVITY SANITARY SEWER      
  PROJECT NUMBER 292-02-666      
46 For Furnishing and Installing Gravity Sanitary Sewer Pipe, as specified, complete in place.      
A 21-inch Sanitary Sewer Pipe      
1 14’ to 16’ Depth 2,366 $56.15 $132,850.90
2 16’ to 18’ Depth 1,016 $57.70 $58,623.20
3 18’ to 20’ Depth 519 $59.50 $30,880.50
4 20’ to 22’ Depth 135 $62.85 $8,484.75
5 22’ to 24’ Depth 38 $67.25 $2,555.50
B 18-inch Sanitary Sewer Pipe      
1 0’ to 6’ Depth 30 $49.60 $1,488.00
2 6’ to 8’ Depth 10 $51.15 $511.50
3 8’ to 10’ Depth 1,061 $53.00 $56,233.00
4 10’ to 12’ Depth 3,596 $56.35 $202,634.60
5 12’ to 14’ Depth 1,328 $60.75 $80,676.00
6 14’ to 16’ Depth 637 $72.25 $46,023.25
7 16’ to 18’ Depth 45 $84.15 $3,786.75
8 18’ to 20’ Depth 45 $96.50 $4,342.50
C 15-inch Sanitary Sewer Pipe      
1 8’ to 10’ Depth 1,013 $50.75 $51,409.75
2 10’ to 12’ Depth 74 $54.10 $4,003.40
D 12-inch Sanitary Sewer Pipe      
1 0’ to 6’ Depth 129 $43.10 $5,559.90
2 6’ to 8’ Depth 1,112 $43.90 $48,816.80
3 8’ to 10’ Depth 2,341 $45.75 $107,100.75
4 10’ to 12’ Depth 1,011 $49.10 $49,640.10
5 12’ to 14’ Depth 1,274 $53.50 $68,159.00
6 14’ to 16’ Depth 311 $64.60 $20,090.60
7 16’ to 18’ Depth 56 $76.90 $4,306.40
E 8-inch Sanitary Sewer Pipe      
1 0’ to 6’ Depth 12 $37.90 $454.80
2 6’ to 8’ Depth 83 $38.70 $3,212.10
3 8’ to 10’ Depth 215 $40.50 $8,707.50
4 10’ to 12’ Depth 184 $43.85 $8,068.40
5 12’ to 14’ Depth 14 $48.25 $675.50
47 For Substituting Ductile Iron Pipe, as specified, complete in place.      
A 24” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 47) 105 $57.70 $6,058.50
B 18” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 47) 753 $25.85 $19,465.05
C 12” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 47) 530 $15.15 $8,029.50
D 8” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 47) 60 $11.35 $681.00
48 For Basic 0’ to 6’ Depth, Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes      
1 Bolted Down Frame and Cover 47 $1,460.00 $68,620.00
B 5-foot Diameter Manholes      
1 Bolted Down Frame and Cover 12 $2,290.00 $27,480.00
49 For Extra Depth, All Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes 342 $113.00 $38,646.00
B 5-foot Diameter Manholes 140 $157.00 $21,980.00
50 For furnishing and installing 5-inch diameter Vent Pipe, as specified, complete in place.      
A For Basic 0’ to 6’ Depth Manholes 24 $1,002.00 $24,048.00
B For Extra Depth, all Manholes 96 $192.00 $18,432.00
51 For Furnishing and Installing Granular Bedding and Stabilization, as specified, complete in place.      
A Type II Bedding 1,020 $1.65 $1,683.00
B Type III Bedding 19,020 $1.65 $31,383.00
52 For Furnishing and Installing Stone Bedding and Stabilization, as specified, complete in place. (For Undercut Excavation as directed by the Engineer) 1,000 $24.00 $24,000.00
53 For Solid Rock Excavation, as specified, complete in place ($40/CY minimum). 8,000 $40.00 $320,000.00
Items 54 through 57 are for non-guaranteed bores.        
54 For Furnishing and Installing (Dry-Bore) with Steel Encasement, as specified, complete in place.      
A 30-inch Diameter Casing (0.312”) 440 $623.00 $274,120.00
B 24-inch Diameter Casing (0.250”) 128 $770.00 $98,560.00
C 18-inch Diameter Casing (0.250”) 48 $625.00 $30,000.00
D Concrete Barriers (Bore Pits) 190 $3.60 $684.00
55 For Mobilization, Excavation and Backfill for Bore Installation, as specified, complete in place. 8 $4,185.00 $33,480.00
56 For Grouting Incomplete Encasing Pipe, as specified, complete in place      
A 30-inch Encasing Pipe (0.312”) 110 $283.00 $31,130.00
B 24-inch Encasing Pipe (0.250”) 32 $265.50 $8,496.00
C 18-inch Encasing Pipe (0.250”) 12 $135.00 $1,620.00
57 For Installing 48-inch Tunnel (12 Gauge), Anchoring the Carrier Pipe, and necessary mortar end sealing, as specified, complete in place. The unit price will not be less than the unit bid price for boring.      
A 30-inch Encasing Pipe (0.312”) 110 $1,795.00 $197,450.00
B 24-inch Encasing Pipe (0.250”) 32 $1,795.00 $57,440.00
C 18-inch Encasing Pipe (0.250”) 12 $1,795.00 $21,540.00
Items 58 through 60 are for guaranteed bores.        
58 For Furnishing and Installing (Dry-Bore) with Steel Encasement (guaranteed casing installation), as specified, complete in place.      
A 30-inch Diameter Casing (0.312”) 186 $1,257.00 $233,802.00
B 24-inch Diameter Casing (0.250”) 80 $1,235.00 $98,800.00
C Concrete Barriers (Bore Pits) 60 $3.60 $216.00
59 Not Used      
60 Not Used      
61 For Furnishing and Installing Soft Shoulder Signs as specified, complete in place. 18 $143.00 $2,574.00
62 For Clearing, Grubbing & Disposal of Debris, as specified, complete in place 18,655 $4.20 $78,351.00
63 For Constructing and Maintaining Various Erosion Control Devices, as specified.      
A Silt Fence 25,800 $2.10 $54,180.00
B Temporary Stream Crossings/Stream Bank Restoration 4 $5,390.00 $21,560.00
C Temporary Construction Entrance 6 $1,080.00 $6,480.00
D Jute Blanket 1,000 $2.15 $2,150.00
E Curlex Blanket 3,000 $2.50 $7,500.00
F Temporary Diversion Ditch 18,000 $1.25 $22,500.00
G Temporary Sediment Trap      
1 Temporary Sediment Trap 200-300 CF 27 $302.50 $8,167.50
2 Temporary Sediment Trap 700 - 1,000 CF 25 $350.00 $8,750.00
3 Temporary Sediment Trap 2,500 - 3,000 CF 11 $390.00 $4,290.00
4 Temporary Sediment Trap 4,500 + CF 5 $430.00 $2,150.00
64 For Fertilizer, Seed, and Mulching, as specified complete in place. 120,000 $0.55 $66,000.00
65 For Furnishing and Installing Stone Rip-Rap, as specified, complete in place. 1,800 $30.25 $54,450.00
66 For Testing for Exfiltration, as specified complete.      
A Sanitary Sewer Pipe      
1 21-inch Pipe 4,075 $0.90 $3,667.50
2 18-inch Pipe 6,778 $0.80 $5,422.40
3 15-inch Pipe 1,087 $0.75 $815.25
4 12-inch Pipe 6,234 $0.70 $4,363.80
5 8-inch Pipe 508 $0.60 $304.80
B Manholes      
1 4-foot Diameter Manholes 47 $80.00 $3,760.00
2 5-foot Diameter Manholes 12 $80.00 $960.00
  Sum for project 292-02-666     $3,065,535.75
  CLEAR CREEK GRAVITY SANITARY SEWER      
  PROJECT NUMBER 200-03-569      
67 For Furnishing and Installing Gravity Sanitary Sewer Pipe, as specified, complete in place.      
A 12-inch Sanitary Sewer Pipe      
1 6’ to 8’ Depth 22 $41.65 $916.30
2 8’ to 10’ Depth 130 $43.10 $5,603.00
3 10’ to 12’ Depth 12 $45.75 $549.00
4 12’ to 14’ Depth 28 $49.10 $1,374.80
B 8-inch Sanitary Sewer Pipe      
1 6’ to 8’ Depth 99 $37.90 $3,752.10
2 8’ to 10’ Depth 248 $39.55 $9,808.40
3 10’ to 12’ Depth 270 $49.50 $13,365.00
4 12’ to 14’ Depth 492 $43.85 $21,574.20
5 14’ to 16’ Depth 476 $48.25 $22,967.00
68 For Substituting Ductile Iron Pipe, as specified, complete in place.      
A 12” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 66) 192 $7.40 $1,420.80
B 8” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 67) 1,209 $9.90 $11,969.10
69 For Basic 0’ to 6’ Depth, Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes      
1 Bolted Down Frame and Cover 7 $1,320.00 $9,240.00
70 For Extra Depth, All Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes 65 $112.45 $7,309.25
71 For Furnishing and Installing Granular Bedding and Stabilization, as specified, complete in place.      
A Type III Bedding 1,796 $1.65 $2,963.40
72 For Furnishing and Installing Stone Bedding and Stabilization, as specified, complete in place. (For Undercut Excavation as directed by the Engineer) 80 $24.00 $1,920.00
73 For Clearing, Grubbing & Disposal of Debris, as specified, complete in place 1,777 $4.20 $7,463.40
74 For Constructing and Maintaining Various Erosion Control Devices, as specified.      
A Silt Fence 1,800 $2.10 $3,780.00
B Temporary Stream Crossings/Stream Bank Restoration 1 $5,390.00 $5,390.00
C Temporary Construction Entrance 1 $1,080.00 $1,080.00
D Curlex Blanket 210 $2.50 $525.00
E Temporary Diversion Ditch 1,500 $1.25 $1,875.00
F Temporary Sediment Trap      
1 Temporary Sediment Trap 200-300 CF 4 $302.50 $1,210.00
75 For Fertilizer, Seed, and Mulching, as specified complete in place. 10,300 $0.55 $5,665.00
76 For Furnishing and Installing Stone Rip-Rap, as specified, complete in place. 150 $30.25 $4,537.50
77 For Testing for Exfiltration, as specified complete.      
A Sanitary Sewer Pipe      
1 12-inch Pipe 192 $0.60 $115.20
2 8-inch Pipe 1,604 $0.75 $1,203.00
B Manholes      
1 4-foot Diameter Manholes 7 $80.00 $560.00
  Sum for project 200-03-569     $148,136.45
  CLEAR CREEK GRAVITY SANITARY SEWER      
  PROJECT NUMBER 090-03-601      
78 For Furnishing and Installing Gravity Sanitary Sewer Pipe, as specified, complete in place.      
A 8-inch Sanitary Sewer Pipe      
1 0’ to 6’ Depth 15 $44.10 $661.50
2 6’ to 8’ Depth 321 $46.40 $14,894.40
3 8’ to 10’ Depth 90 $49.15 $4,423.50
79 For Substituting Ductile Iron Pipe, as specified, complete in place.      
A 8” Ductile Iron Pipe (Pressure Class 250) – (Add onto Item 87) 198 $9.85 $1,950.30
80 For Basic 0’ to 6’ Depth, Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes      
1 Bolted Down Frame and Cover 2 $1,365.00 $2,730.00
81 For Extra Depth, All Manholes as specified, backfilled, complete in place.      
A 4-foot Diameter Manholes 7 $113.00 $791.00
82 For Furnishing and Installing Grannular Bedding and Stabilization, as specified, complete in place.      
A Type III Bedding 426 $1.65 $702.90
83 For Furnishing and Installing Stone Bedding and Stabilization, as specified, complete in place. (For Undercut Excavation as directed by the Engineer) 20 $24.00 $480.00
84 For Furnishing and Installing (Dry-Bore) with Steel Encasement, as specified, complete in place.      
A 30-inch Diameter Casing (0.312”) 159 $537.00 $85,383.00
B Concrete Barriers (Bore Pits) 50 $3.60 $180.00
85 For Mobilization, Excavation and Backfill for Bore Installation, as specified, complete in place. 1 $4,185.00 $4,185.00
86 For Grouting Incomplete Encasing Pipe, as specified, complete in place      
A 30-inch Encasing Pipe (0.312”) 39 $282.00 $10,998.00
87 For Installing 48-inch Tunnel (12 Gauge), Anchoring the Carrier Pipe, and necessary mortar end sealing, as specified, complete in place. The unit price will not be less than the unit bid price for boring. 39 $1,806.00 $70,434.00
88 For Furnishing and Installing Soft Shoulder Signs as specified, complete in place. 4 $143.00 $572.00
89 For Clearing, Grubbing & Disposal of Debris, as specified, complete in place 426 $4.20 $1,789.20
90 For Constructing and Maintaining Various Erosion Control Devices, as specified.      
A Silt Fence 230 $2.10 $483.00
B Temporary Construction Entrance 2 $1,080.00 $2,160.00
C Jute Blanket 50 $2.15 $107.50
D Temporary Diversion Ditch 200 $1.25 $250.00
E Temporary Sediment Trap      
1 Temporary Sediment Trap 200-300 CF 2 $302.50 $605.00
91 For Fertilizer, Seed, and Mulching, as specified complete in place. 1,700 $0.55 $935.00
92 For Testing for Exfiltration, as specified complete.      
A Sanitary Sewer Pipe      
1 8-inch Pipe 426 $0.60 $255.60
B Manholes      
1 4-foot Diameter Manholes 2 $156.00 $312.00
93 For Removal and Replacement of Landscape Items, as specified, as directed by the Engineer, complete in place. 1 $5,000.00 $5,000.00
  Sum for project 090-03-601     $210,282.90
  CLEAR CREEK BASIN INTERIM PUMPING STATION AT BARTLETT ROAD AND CLEAR CREEK – PROJECT NUMBER 292-02-673:      
94 Clear Creek Pumping Station – All costs for all labor, materials, equipment, supplies, permits, fees, taxes, insurance, other miscellaneous costs, profit and overhead, both direct and indirect, for completion of all Work except for those Bid Items previously listed. 1 $780,000.00 $780,000.00
  Base Bid     $5,732,958.50
95 Mobilization 1 $115,000.00 $115,000.00
96 Contingency Allowance (2% of Contract Subtotal plus Mobilization)     $116,959.17
  Total Base Bid     $5,964,917.67
97 Deductive Bid Alternate A - Elimination of Clear Creek Basin Interim Pump Station at Bartlett Rd and Clear Creek (Bid Item #94) plus associated mobilization and 2% contingency allowance. 1 $800,000.00 $800,000.00
 
 
Concord Engineering & Surveying Inc.
45 Spring St SW - Concord, NC 28025 - 704-786-5404
www.concordengineering.com